Specialist in Marine and Coastal Construction

Port of Sale - Stage 1

Date: (November 2003 — June 2004)

Client: Wellington Shire Council, Sale, Victoria

Project Value: $2,200,000

Works included:

  • Timber and steel tube piling works.
  • Construction of 140 lineal metres of timber boardwalk and 2 No Jetty structures.
  • Sewerage and drainage reticulation works.
  • Construction of exposed aggregate concrete footpaths (700 lineal metres) associated kerb and channel works, concrete approaches and 150 lineal metres of structural retaining wall.
  • Construction of Convenience Centre including toilets, plant room, BBQ and furniture.
  • General marine works including dredging, installation of screw piles for structural retaining wall, upgrade of boat pump out facility and rock stabilisation works.
  • Installation of aluminium gangway and floating pontoon system.
  • Electrical and street lighting works.
  • Bulk earthworks and General landscaping works
ps #2
ps #3 ps #5
ps #4
[Apollo Bay 2001]   [Apollo Bay Marina 2008]   [Altona Harbour 2001]   [Altona Boat Ramp 2008]   [Barwon Heads 2004]   [Beaumaris 2002]   [Brighton Beach 2003]   [Brighton Beach]   [Geelong 2002]   [Port of Sale 2004]   [Port Melbourne Beach 1999]   [River Bank Work 2002]   [Rye Beach 1999]   [San Remo 1997]   [St Kilda Beach 2001]   [Werribee South 2002]   [Williamstown Groyne 2000]   [Yarra River 2006

Harbour Construction

Jetty Construction

Breakwater Construction

Pile Installation

River Bank Stabilisation

Dredging

Board Walk Construction

Car Park/ Civil Works

Floating Pontoon Installation

Insitu and Precast Concrete Works

CCFlogo   ielogo

footer_r1_c1

footer-blue          Home      About Us      Services      Recent Projects      Resources      Project Delivery      Contact Us