Patterson River Boat Ramp Construction and Associated Works

Date: February 2008 to June 2008
Client: Park’s Victoria
Project Value: $1.45 Million

Works included:

  • Demolition of 2 existing concrete boat ramps and 160lm of concrete/timber retaining wall
  • Site establishment of plant and equipment including piling equipment
  • Supply and pile driving of 24 No, 508 mm dia, 12lm long steel piles for both boat ramps.
  • Supply and installation of boat ramp precast concrete headstock’s and bearer’s
  • Supply and installation of boat ramp precast concrete panels including fluted surface profile and edge kerbing
  • Supply and construction of insitu concrete works
  • Supply and driving of  36 No 12 lm long epoxy coated 250 UC piles for retaining wall
  • Supply and installation of precast concrete retaining wall panels
Patterson River Stage 2006
Paterson River View
Patterson River 018

Harbour Construction

Jetty Construction

Breakwater Construction

Pile Installation

River Bank Stabilisation

Dredging

Board Walk Construction

Car Park/ Civil Works

Floating Pontoon Installation

Insitu and Precast Concrete Works